OHE Breakdown Restoration — Temporary Diversions, Speed Restrictions & Procedure

Electrical Engineering Traction Distribution Chapter 19/87 18 min read Source: Official
हिन्दी में पढ़ें

Create a free account to track your reading, save important notes and practise this topic.

Officers and Supervisors Proceeding to Site

On receipt of information about an OHE breakdown, JE/SSE (OHE) and DEE/ADEE (TrD) shall proceed by the QUICKEST AVAILABLE means to the accident scene. Sr.DEE(TrD) should also proceed to site if circumstances require personal supervision/direction. In the event of a MAJOR breakdown likely to interrupt traffic for MORE THAN 12 HOURS, CEDE should also proceed to site to supervise restoration.

Restoration of traffic after an accident/breakdown is the responsibility of the DIVISION AS A WHOLE — the Electrical Department officer in-charge should seek assistance from Engineering, Traffic, or other officers as necessary, and keep the DRM fully posted. Assistance from a NEIGHBOURING DIVISION's OHE gangs may be sought via ADEE(TRD) or Sr.DEE/DEE(TRD) — officers receiving such requests should treat them as of UTMOST IMPORTANCE.

Communication & Site Assessment

The Officer/Supervisor in-charge of repair work must maintain CONTINUOUS communication with TPC — an intelligent person should be posted to man the nearest emergency telephone socket continuously, since the emergency telephone circuit has NO PROVISION for TPC to ring the site — field staff must stay on-call until service is fully restored.

The FIRST Supervisor/Officer reaching site makes a quick assessment of damage extent and restoration time, ascertains from TPC what gangs/equipment are already dispatched, and requests additional resources if warranted — isolation and repair work should START in the meanwhile, without waiting for these details to be finalized. In MAJOR breakdowns affecting main-line traffic, Sr.DOM/DOM of the Division should PERSONALLY take over traffic-regulation arrangements.

Preservation of Evidence & Safety Rules

When a pantograph gets entangled with OHE, it is often DIFFICULT to establish whether the fault originated in the pantograph or the OHE. The first Electrical Department Officer/Supervisor at such a site must make a careful note of ALL relevant details, prepare a sketch, and arrange for preservation of evidence useful for investigating the cause.

While speed is essential in emergency working, safe-working rules must NEVER be infringed — repair work may commence ONLY after an emergency power block has been obtained and all other staff-protection precautions taken. On completion, the power block is cancelled per prescribed procedure.

Temporary Repairs, Diesel Clearance & the Wiring Train

Initial repairs should be kept to the BAREST MINIMUM necessary for restoring traffic with least delay — work proceeding simultaneously at many points. After temporary repairs, the Officer/Supervisor in-charge should personally check the whole area, impose necessary speed restrictions, and arrange permanent repairs at the earliest opportunity. If restoration of electric traction is unlikely soon, the line should be cleared for DIESEL TRACTION as soon as possible, with full staff-protection precautions once diesel traction is introduced.

Temporary Diversion Structure — Full Construction Detail

When derailments/accidents require temporary diversions (to clear traffic on non-electric traction while resuming electric traction quickly, without waiting for the main line to be recommissioned), a specific portal-type structure is used — genuinely detailed, real construction specifications:

Advantage of This ConstructionDetail
CheapLow-cost materials
LightStructures weigh LESS THAN 150 kg — 4 men can erect or dismantle them easily
Fast to erectNo foundation excavation needed, so no time lost
ReusableCan be dismantled and re-erected at new sites quickly
No extra speed restrictionTraffic moves at the permanent-way-imposed speed restriction only
Easily sourcedMaterials/fabrications are easily manufactured in workshops and stocked at depots for emergency use
🎯
Exam Focus — The Portal Structure's Dimensional Chain
A genuine chain of nested dimensions worth memorizing in sequence: 80mm GI pipe (the upright) sits inside a 150mm MS pipe (the sleeve), welded to a 450mm×450mm×10mm MS base plate, bolted with 10mm bolts to a 4880mm crossing sleeper under the rails. Contact wire anchors at 6m height on existing masts. Structure weight <150kg, erected by 4 men. These numbers nest logically from smallest (pipe diameter) to largest (sleeper length) — a useful memory anchor.

Temporary Speed Restrictions — Real Timelines by Damage Type

Damage TypeSpeed RestrictionTime to Full Restoration
Temporary mast provided (foundation needs 5-6 days curing before OHE shifts to it)15-40 kmph (per site conditions)~10 days from imposition (subject to block availability)
Mast bent (straightened using tirfor)30-60 kmph (per site conditions/stagger profile)3-4 days
Extensive OHE damage from panto entanglement, masts unaffected (attended with temporary droppers)30-60 kmph (per site conditions)~4 days (subject to extent of damage and block availability)
🎯
Exam Focus — Why Temporary Mast Takes Longer Than Mast Straightening
The temporary-mast case (~10 days) takes roughly 2-3x longer than the bent-mast (3-4 days) or panto-entanglement (~4 days) cases — and the reason is stated explicitly: it's not track/OHE work that's slow, it's FOUNDATION CURING TIME (5-6 days) for the new permanent mast before the OHE can even be shifted onto it. The other two cases involve no new foundation at all, which is exactly why they resolve faster despite sometimes allowing a similarly low speed restriction (30-60 kmph).

Funds, Logging & Final Precautions

Funds for breakdowns may be drawn from STATION EARNINGS (per Para 714, Indian Railways Permanent Way Manual) — for daily labour payment, tools/materials not suppliable in time by Stores, and food for engineering labour at the accident/breach site (free food is permitted in special circumstances, at Administration discretion, within a prescribed per-head-per-day expenditure limit). The Accounts Officer must be advised IMMEDIATELY BY TELEGRAM of each sum drawn; a clear receipt stating the purpose is required; a complete account with pay sheets/vouchers is submitted at the earliest date; all labour payments are witnessed by the Assistant Engineer at site.