OHE Quick Reference Parameters & Safety Precautions

Electrical Engineering Traction Distribution Chapter 83/87 18 min read Source: Official
हिन्दी में पढ़ें

Create a free account to track your reading, save important notes and practise this topic.

This chapter combines a quick-reference sheet of critical OHE numeric parameters (the kind of single-page 'cheat sheet' worth memorizing wholesale), and the official 28-point safety precaution list for anyone working on OHE.

Contact Wire Heights

Location / ConditionHeight
Normal, at support — regulated OHE (pre-sag 100mm)5.60 m
Normal, at support — regulated OHE (pre-sag 50mm)5.55 m
Normal, at support — unregulated OHE (temp. range 4°-65°C)5.75 m
Normal, at support — unregulated OHE (temp. range 15°-65°C)5.65 m
Minimum, at loco inspection pit5.80 m
Minimum, at level crossing5.50 m
Height gauge at level crossing4.67 m
Minimum, at overline structure4.92 m

Contact Wire Diameter, Stagger & Slope

ParameterValue
New contact wire diameter12.24 mm
Condemned diameter — main line8.25 mm
Condemned diameter — loop/yard lines8.00 mm
Stagger — tangent track±200 mm
Stagger — curved track±300 mm
Stagger — catenary wire at support (single cantilever, tangent)0
Stagger — section insulator0 or ±100mm max
Stagger — PTFE neutral section at support0
Max permissible slope of contact wire — main line3 mm/metre
Max permissible slope of contact wire — in yards5 mm/metre

Overlaps, Turnouts & Implantation

ParameterValue
Gap between parallel contact wires — uninsulated overlap200 mm
Gap between parallel contact wires — insulated overlap500 mm
Height of turnout OHE contact wire above main line contact wire5 cm (+50mm)
Track separation at turnout/crossover at obligatory structure150-700 mm
Minimum implantation at obligatory structure (mast supporting >1 OHE)3 m
Normal implantation (standard)2.50 m ±0.03
Minimum implantation (critical, needs CEE approval)2.36 m
Minimum implantation on platform4.75 m
Normal encumbrance (for 72m span)1.4 m
Overlap-type turnout span≤54 m
Crossed-type equipment (facing turnouts) anchor span restriction54 m

Electrical Clearances

Clearance TypeValue
Short-time minimum vertical electrical clearance270 mm
Short-time minimum horizontal electrical clearance220 mm
Long-time minimum vertical electrical clearance320 mm
Long-time minimum horizontal electrical clearance320 mm
Minimum working clearance2 m

Jumpers, Droppers & Earthing

ParameterValue
Earthing resistance — FOB/ROB/Girders/Bridges/Platform shed/overline structures10 Ω
'C' jumper wire — cross-section / length50 mm² / 1.7 m
'F' jumper wire — cross-section / length50 mm² / 1.6 m
'G' jumper wire — cross-section / length105 mm² / 3.5 m
Distance of 'G' jumper from obligatory mast, towards overlap side5.6 m
Fixed length of dropper wire105 mm
Distance of first dropper from support2.25 m
Minimum length of dropper in a span150 mm

Section Insulator Geometry

ParameterValue
Contact wire-to-runner distance, either sideNot less than 220 mm
Axial distance, catenary-to-contact wire at section insulator locationNot less than 450 mm
Section insulator located beyond point where track-centre distance is≥1.65 m
Swept-zone clearance of section insulator — trailing side1.726 m
Swept-zone clearance of section insulator — facing side1.60 m

Tension Lengths, Spans & ATD Values

ParameterValue
Maximum tension length — regulated OHE1500 m
Maximum tension length — unregulated OHE2000 m
Normal sag of regulated OHE100 mm
Maximum span length on tangent track (regulated OHE)72 m
Difference in length of adjacent spans on main line — max18 m
ZY value, winch-type ATD, at half tension length (750m) at 35°CZ = 1250, Y = 2500 (mm)
XY value, 3-pulley type ATD, at half tension length (750m) at 35°CX = 750, Y = 2500 (mm)
Mast leaning — attend if leaning at TOP exceeds15 cm
Isolator — distance between male/female contact, open position500 mm ±50
🎯
Exam Focus — Two Different Mast-Leaning Numbers, Two Different Contexts
Don't confuse this sheet's '15cm leaning at TOP → attend' rule with the Cantilever Maintenance chapter's mast-verticality rule (≤3cm OK, ≤5cm watch with a yellow band at 1.85m, >5cm attend). These are genuinely different measurement contexts. If a question doesn't specify which context, the cantilever maintenance figures (3cm/5cm) are tied to an actual documented procedure with a physical marking (yellow band) — treat that as the primary answer unless the question clearly points to a simpler general check.

Safety Precautions While Working on OHE — Full 28-Point List

As OHE voltage is 25kV, the following precautions must be taken by staff working on OHE:

  1. No work shall be done ABOVE or WITHIN 2 METRES of live OHE without a 'Permit to Work'.
  2. Large metallic structures (fencing, structural steel of platforms running parallel to track) develop inductive effects — they must be suitably earthed for safety.
  3. Each working party shall be protected by AT LEAST TWO INDEPENDENT EARTHS, one on each side of the party.
  4. If distance between working parties exceeds 1000 METRES (1 km), an intermediate earth must be provided so no two earths are more than 1000 m (1 km) apart.
  5. Men shall be posted on BOTH sides of the work site to warn of approaching trains on the same and adjacent track.
  6. To earth the OHE: fix the earthing clamp securely to a mast AT LEAST ONE SPAN AWAY, after confirming that mast's mast-to-rail earth bond is intact.
  7. EARTHING SEQUENCE: always fix the earthing clamp to the traction rail or mast FIRST, then hook the top clamp to the OHE being earthed.
  8. REMOVAL SEQUENCE (reverse of above): first remove the hook on the OHE, THEN remove the clamp fixed to rail/mast.
  9. Two sections of conductors, or snapped conductor ends, should be SEPARATELY earthed at TWO points after switching off supply to both parts. Same precaution applies near sectioning points and cut-in insulators.
  10. Neutral sections must be TREATED AS LIVE EQUIPMENT and earthed separately at TWO points on either side of the work party before commencing work.
  11. Work on an isolator: BOTH sides of the isolator should be earthed at TWO points.
  12. No fallen wire shall be touched unless power is switched off AND the wire is suitably earthed.
  13. On electrified track, steel/metallic tape or tape with woven metal reinforcement must NOT be used.
  14. Ropes, come-along clamps, and tirfors should be TESTED ONCE A MONTH in the presence of JE-I (TRD).
  15. All staff should wear HELMETS to protect against dropped tools/equipment.
  16. Staff should wear a SAFETY BELT (rope sling) to protect against inadvertent falls.
  17. Ropes used with ladders must be COTTON OR JUTE — metallic ropes are PROHIBITED. One person must hold the ladder from the ground; the top end must be tied to the supporting structure/conductor to prevent sliding.
  18. Ladders shall never be allowed to fall on or rest against the contact wire.
  19. More than one person shall NOT normally be allowed on a ladder.
  20. Climbing a ladder with wet or slippery footwear is FORBIDDEN.
  21. Use a rope to pass tools/equipment to a person working on a ladder.
  22. No one should stand directly BELOW a ladder work spot.
  23. Anchoring rope strength must NOT be less than that of the cable being anchored.
  24. Staff requesting a power block must correctly identify/describe the exact OHE section requiring shutdown.
  25. If there's ANY doubt in the description, the person requesting a power block must clearly state the track and OHE structure numbers between which work is to be done.
  26. All shutdown/restoration/Permit-to-Work messages over telephone MUST be supported by exchange of PRIVATE NUMBERS and REPEATED TWICE.
  27. Do NOT tie a rope to the rail without taking a traffic block.
  28. It is necessary to take a TRAFFIC BLOCK when working on a tunnel or bridge.
🎯
Exam Focus — Earthing Sequence Is Reversible and Testable Both Ways
A classic sequencing question: while EARTHING, the clamp goes on rail/mast FIRST, then the top clamp hooks onto the OHE. While REMOVING earth, it's the exact REVERSE — the OHE hook comes off first, then the rail/mast clamp. The underlying safety logic: you always want the earth connection established BEFORE the OHE connection, and broken AFTER — so the OHE is never connected to a floating (non-earthed) clamp at any point in the process.

← All Electrical Engineering chapters