These rules are supplementary to the General and Subsidiary Rules (GR/SR). Every OHE maintenance depot, equipment room, switching station, cabin, and related office must display printed boards on electric-shock treatment, and keep First Aid Boxes at every switching station, maintenance depot, OHE Inspection Car, and breakdown vehicle. Ropes, come-along clamps, and Trifor devices must be tested at least once every six months, with records maintained per depot.

Permit to Work

🎯
Exam Focus — The 2m Rule
A Permit to Work must be obtained from TPC (Traction Power Controller) or other authorized person before commencing work on any part of DEAD OHE, or within 2 metres of LIVE OHE — this 2m distance figure is a frequently tested number.

Earthing Before Commencement of Work

Procedure for Providing Temporary Earths — The Exact Sequence

  1. Post men on both sides of the work site to warn of approaching trains on the same and adjacent tracks.
  2. Obtain the Permit-to-Work first, confirming power has been switched off.
  3. Use only a discharge/earthing pole assembly specifically designed for this purpose — flexible cable with at least 40 mm² cross-section, able to withstand short-circuit currents.
  4. Fix the earthing clamp securely to a mast at least one span away, confirming the mast-to-earth-rail bond is intact — check tightness just before connecting the top clamp, since a clamp fixed in advance could have worked loose.
  5. Hook the top clamp securely to the OHE conductor with a snap action, and tie the earthing pole to the mast/structure.
  6. Repeat for the second temporary earth on the other side of the working party.
⚠️
Critical Safety Rule — Never Hook the OHE End First
Never hook the top hook of the earthing cable onto the OHE until the OTHER end has first been connected to earth. Removal follows the exact reverse order — first remove the hook on the OHE, then remove the clamp fixed to the rail/mast/structure. Getting this sequence backwards means briefly handling a cable that could still carry fault current.

Discharge/Earthing Pole Assembly — Precautions

Neutral Sections & Sectioning Points

Neutral Sections must be treated as LIVE equipment and earthed separately at two points on either side of the work party before starting work — even though they're 'neutral' in normal operation. When work involves conductors that aren't electrically bonded (e.g. around a sectioning point), each snapped end could be at a different potential, so each end must be separately earthed at two points.

Ladder Safety Rules

Work Near Parallel Overhead Lines

🎯
Exam Focus — The 8m Rule
No work on any overhead line span running parallel to an electrified track — where the minimum distance to the nearest electrified-track centre-line is less than 8m — may be done without switching off and earthing the 25kV traction line, EXCEPT for 4 specific low-risk items: replacing lamps below the line, painting structures/poles up to 2m from live wires, foundation reinforcement (without prior weakening), and replacing aerial fuses.

Isolators

Isolating switches on the 25kV system must NEVER be opened or closed while current is passing through them. Normally, isolators should only be operated after power supply to the section has been switched off by opening the appropriate interruptor first.

Petroleum Sidings — Special Precautions

Records & Registers

Real, specific registers each depot/sub-depot must maintain: Daily Report of OHE Maintenance, Register for Foot-Patrol Reports, Cantilever Assembly Maintenance Register, Register of Contact Wire Thickness Measurements, Register of Clearance under Over Line Structures, Register of Earth Resistance Measurements, Register of Current Collection Tests, Register of Regulating Equipment, Register for Isolator Switches, Register for Turn Outs and Cross Overs, and Register of Vulnerable Foundations.