This chapter covers the equipment specifically feeding railway traction sub-stations from the 132 kV (or similar) grid interface, and the protection philosophy that keeps faults contained to the smallest possible section.

Protective Relays — What They Detect

CT vs. PT — Don't Mix Them Up
  • Current Transformer (CT) — connected in series with the line, steps high current down to a standard secondary (typically 1A or 5A) for relays/meters.
  • Potential Transformer (PT) — connected in parallel (across the line), steps high voltage down to a standard secondary (typically 110V) for relays/meters.
  • A CT secondary must never be left open-circuited while primary current flows — it can develop dangerously high voltage.
🎯
Exam Focus
A classic trap question: 'What happens if a CT secondary is open-circuited?' — the answer is dangerously high voltage across the open terminals, not zero current as intuition might suggest.